Featured Project

Mission Critical Fuel Oil System – Ashburn Corporate Center Data Center Complex

Project Description:

Tanks Direct was contracted to install multiple 50,000 gallon ACT 100U underground storage tanks and related equipment to provide a mission critical fuel oil system.

Project Highlights:
Ten (10) 10 50,000 gallon underground fuel oil storage tanks
Prefabricated steel double wall piping with FRP coating
FE Petro submersible fuel oil pumps
Fuel Oil Polishing and Cleaning Systems
Integrated fuel oil day tanks and controls
Veeder‐Root tank monitoring and leak detection system
Commissioning, start up, training, and integration with the BMS system

Project Gallery

Trust The Full Service Tank Experts.

Request a Quote